The purpose of Early Production is loading of four storage tanks by gas condensate each with a nominal capacity of 80,000 cubic meters in the EPC3 area. The gas condensate project comes in two lines of 30 inches in the northwest of the site, which includes gas condensate from the upstream refinery.
Then discharge of these reservoirs to be transferred to the SBM export route by using three pumps of P-1001, D, E, F each with a capacity of 2300 rated cubic meters per hour and with a 1 + 2 combination.
Nardis Co., as the contractor for detaile engineering, supply of materials and equipment, construction works, installation and commissioning of 72 hours in the condensate project, initiated an early production plan in two stages, the first stage of the project (Launching the loading path) from October to December 2018 and final stage of the project (launch the SBM line) from January 5 to March 5, 2019